Ф79—Ф630 derusting and anti-corrosion production line

Ф79—Ф630 derusting and anti-corrosion production line

The above is welded with 180# channel steel and the steel plates are 8 mm and 6 mm. The tires are made of pneumatic tires the transmission part is connected by Isuzu drive shaft the power part is 5.5KW*7 sets of motors frequency conversion speed regulation well-known factory reducer.

Features

The main box is made of 8mm thick steel plate the frame part is welded with 180# channel steel the inner guard plate is made of 10 mm thick high-chromium material and the head is made of high-efficiency throwing head.

 

Detailde


derusting and anti-corrosion production line comprising:

1. Pipe conveyor:
12000*1600 5 sets  seven sets of transfer wheels
7500*1600 1 set   five sets of transfer wheels
800*1600 6 sets   transfer wheels per set
The above is welded with 180# channel steel, and the steel plates are 8 mm and 6 mm. The tires are made of pneumatic tires, the transmission part is connected by Isuzu drive shaft, the power part is 5.5KW*7 sets of motors, frequency conversion speed regulation, well-known factory reducer.

2 , descaling machine:
The main box is made of 8mm thick steel plate, the frame part is welded with 180# channel steel, the inner guard plate is made of 10 mm thick high-chromium material, and the head is made of high-efficiency throwing head. The power part adopts 2*37KW motor, and the lifting part adopts 3KW motor with cycloidal pin reducer vertical belt hoist. The dust removal device adopts two-stage dust removal, one is a cyclone dust collector, and the second is a bag filter. Equipped with two 4KW fans.
 

Name Parameter
Cleaning effect 1-6m/min
 Number of blasting machines 2 sets
Shot volume 2*750kg/min
      Shot blaster power 2*37kw
      Hoist lift 60t/h
      Separator separation 60t/h
Total air volume 7500m ³ / h
       Total power 90kw
 
3 , medium frequency power supply heating:
It is equipped with two medium frequency heating equipments of 250KW and 500KW . Before using 250KW for the descaling machine, remove the surface moisture of the steel pipe and improve the descaling effect. 500KW is used for external epoxy powder coating. The specially designed control circuit is used to ensure the temperature of the steel pipe is stable. Both units have one sensor and two 3.5 m water cables.
     500kw parameters:

Name Parameter Name Parameter
Input voltage 380V Output maximum voltage 780V
Input Current 850A Output maximum current 1000A
Input frequency 50HZ Output frequency 500HZ ~ 800HZ
250kw parameters:
Name Parameter Name Parameter
Input voltage 380V Output maximum voltage 780V
Input Current 450A Output maximum current 500A
Input frequency 50HZ Output frequency 500HZ ~ 800HZ
 
4 , secondary descaling device:
The burr and rust of the outer wall of the pipeline are removed, the power is 4KW , and the dust driving power is 1.5KW .
 
5. Pipeline derusting line:
The belt sanding machine is 15 meters long and has an overhead setting. The power is 5.5KW . The sandblasting tank adopts four-way sandblasting with a gun length of 12M.
Highly wearable tips. The driving power of the trolley is 3KW, and the rail frame is welded by 120# channel steel, with a length of 17M and a width of 1.3M .
6 . Pipeline spray liquid coating line (single and double components ) :
     The single and double component coatings use one production line, and the walking trolley is a flatbed truck, which is convenient for replacing the material bucket. Car power
For 3KW , the walking frame is welded with 100# channel steel, the length is 15M and the width is 1.2M . (single and double component tips, buckets,
Spraying machine and material pipe are provided by Party A).
7 . Pipeline platform:
The total length of the three release platforms is 72M , which is produced by Party A.